The developer checklist, answered
This is the list a site selection team works through. Every item has an answer, including the items where the answer is that work remains. Nothing is left blank to be found later.
In place today and verifiable now
Underway, with a defined path
Requires survey, counsel or a counterparty input
Power, fuel, water, site, regulatory, counterparty
1 · Power and generation
2 · Fuel supply
3 · Water
4 · Site and land
5 · Regulatory and community risk
6 · Counterparty and structure
Sources. Operator data: Pronghorn operator GIS database, February 2026, and operator-reported production. Transmission, substations and gas pipelines: HIFLD. Generation inventory: EIA-860. Carrier facilities and autonomous system numbers: PeeringDB. Climate: NOAA 1991 to 2020 normals. Tax provisions: Wyoming Business Council, W.S. §39-15-105 and §39-16-105. Interconnection queue volume, median duration and completion rate: Lawrence Berkeley National Laboratory, Queued Up: 2026 Edition, as of year-end 2025. ERCOT large-load queue volume and the August 2026 approval pause: ERCOT and PUCT filings and contemporaneous reporting, 3 and 4 August 2026. ERCOT peak demand: US Energy Information Administration.
Basis of presentation. Volumes are operator-reported. Installed capacity, schedule and the resource statement reflect Pronghorn’s current development plan and are subject to field development, equipment delivery, permitting and the timing of a signed offtake. Distances are straight-line from the Energy Park coordinate. Fiber corridors are indicative alignments along Interstate 90 and are not surveyed cable routes. Grid capacity and interconnection timing are as indicated by Powder River Energy Corporation and Bison and are subject to confirmation. Nothing on this site constitutes an offer, a commitment, or a reserve report.
What sits behind the wall
The public site is complete on site fundamentals and deliberately silent on commercial terms. An executed mutual non-disclosure agreement opens the rest.
Commercial
The institutional information sheet, with power price basis, levelized cost, projected cash flows, capital plan, tenor and escalation structures, the generation supply agreement and letters of support.
Technical
Reserve report, field development schedule by unit, unit-level generation specifications and delivery slots, permit application status, and the full GIS package for Google Earth.
Site visit
Walk the Energy Park, the Barber Creek yard and the header interconnects, and meet the field team that runs the asset.
Google Earth package available
The infrastructure platform as a Google Earth file: Energy Park, 230 kV mesh and substation distances, bidirectional gas headers, water network, fiber corridors and asset footprint, each with its own detail panel. Field-level layers for wells, laterals, electric distribution and water storage are included and switched off by default.
Pro or Web
A load profile is enough to begin.
Send target megawatts at first energization, a ramp schedule and a cooling approach. Pronghorn returns a generation block plan, a field development sequence, a water allocation and a term sheet across power, land and fuel. Capital and structure inquiries reach the same team.